Why Building a Pool Takes 6 Weeks — And Why That’s a Good Thing

  • Writer: Simone
    Simone
  • Jul 14
  • 2 min read
ree

At GW Oliver, we’re known for delivering high-end, custom pools with an efficient, streamlined build process. One of the most common questions we get is:“Why does it take about six weeks to build a pool?”

The short answer? Because we do it right.

The slightly longer answer? Gunite pools require time to cure properly—at least 28 days—and we use that time wisely to complete surrounding work so the project keeps moving forward.


Why the 28-Day Gunite Cure Matters

Gunite is the strong, steel-reinforced concrete shell of your pool. Once applied, it doesn’t just dry—it cures. This is a chemical process that slowly strengthens the shell, ensuring it performs well for decades.

Rushing this phase can cause surface cracking or structural problems later. That’s why we give the shell the full 28 days to cure, even as other aspects of your project continue around it.


Your Pool Build: A Week-by-Week Breakdown

Here’s how a typical 6-week pool build at GW Oliver unfolds:

Week 1 – Excavation & Gunite

  • Excavate the pool and form the structure

  • Install rebar

  • Apply gunite shell

Week 2 – Tile & Coping

  • Begin installing pool tile and coping around the edge

  • Shell begins curing process

Week 3 – Drainage & Deck Sub-Slab

  • Install drainage infrastructure

  • Pour concrete sub-slab for decking areas

Week 4 – Equipment Set & Feature Construction

  • Set pool equipment

  • Begin finish work on decking

  • Build water feature walls, fire features, and any other vertical elements

Week 5 – Final Utilities & Prep for Finish

  • Wire pool equipment and make gas connections

  • Install backflow preventers

  • Final grading and surface prep for interior finish

Week 6 – Plaster & Pool Fill

  • Apply interior finish (plaster, pebble, etc.)

  • Fill the pool and balance the water

  • Final walkthrough and pool start-up


Fast Doesn’t Always Mean Smart—But We Do Both

At GW Oliver, we’ve refined our process over decades. While some builders take shortcuts or skip curing time, we prioritize long-term performance. Our 6-week timeline allows us to maintain the highest quality standards without unnecessary delays.

We don’t just build pools—we build beautiful, lasting outdoor experiences.


Pools Are a Major Investment—Choose a Builder Who Gets It Right

A swimming pool is more than a backyard upgrade—it's a significant investment in your home, lifestyle, and family time. Whether you’re planning to entertain, relax, or create a space for your kids to make lifelong memories, a pool should be built to last.

That’s why choosing the right builder matters.You need someone who understands the technical details of gunite application, proper curing times, equipment sizing, drainage, and finish work. At GW Oliver, we don’t just build pools—we engineer and craft outdoor spaces with the same care and precision you’d expect in the construction of your home.

We’ve spent over 20 years refining our process to deliver both beauty and performance. When corners are cut or timelines are rushed, those mistakes may not show up right away—but they almost always lead to issues down the road.


Ready to Take the First Step?

Let’s bring your backyard vision to life—with craftsmanship, care, and a timeline you can count on. Contact us today to get started.

 
 
 

Comments


NPTLogo_White_2020.png

Creating luxury outdoor living spaces and pools in Texas, and along the Gulf Coast. 

From residential projects to

world-class resorts, multifamily developments  and aquatic training centers,

GW Oliver can handle it all! 

(225) 757-5577
9362 Interline Ave 
Baton Rouge, LA 
70809
Let's Get Social 
  • Facebook
  • Instagram
  • LinkedIn
  • Pinterest
bottom of page